Clearance of site and formation of new levels using gabion baskets as engineered wall support. A combination of recycled and new aggregates was used ...
Due to heavy use and sever erosion, mechanical regrading and the introduction of grips to divert water from the pathways was carried out over several ...
This scheme was implemented to prevent silt being washed into the Adams Hill Locality, it comprised of a 1 metre wide by 1 metre deep channel with flo...
One of several pools we have restored on the estate. This the Mirror pond, restored after desilting. Nicospan geotextile was installed on bank edges t...
Remedial works to Public right of way affected by Badger activity
The following sequence of images shows works undertaken by Elc for Worcestershire C...
Leylands Farm fishing pool Pelsall,Walsall was the subject of a grant funded project jointly with Walsall MBC and Environment Agency.
A local fishing...
As part of a section 106 agreement funding was in place to improve some local wildlife pools at Fibbersley Nature Reserve, Willenhall for Walsall Coun...
Elc constructed new access paths using recycled aggregates and round timber felled on site to act as revetments for pathways. The project was led by t...
Forestry/Conservation Works at Hangman's Hill, Malvern for Malvern Hills Conservators Elc were engaged with the task of clearing scrub and semi mature...
A private client instructed us to create an artificial Badgers sett within his grounds close to the River Severn Worcester. The purpose for which wa...
This dam which formed a series of pools originally intended to supply the Scythe mill industry in Belbroughton over topped in a severe downfall of rai...
Merrions Wood Trust,Walsall awarded us a job of building a new spilway to maintain water levels in an historic pool and also assist in retaining water...
Elc were given the job of constructing a Gabion wall to retain a garden.The previous bank and wall had subsided due to erosion and sustained wet weath...
As part of a network of improvement works on bridleways for Worcestershire County Council, regrading, drainage and surfacing works have been implement...
Mobile elevated working platform (Mewp)
We attended to mature Poplars on a countrypark site deemed unsafe by tree survey and compromising safety of n...
We were asked to clear this site which had outline planning permission for residential development and provide a cost effective temporary fence for wh...
As part of the NIA (Nature improvement area) project across the Black Country Elc Contractors Ltd were successful in winning woodland management thinn...
Our forwarding unit in operation at Warley Woods in December 2013.
The thinned timber Birch and Sycamore totalled about 100 tonnes and was processed ...
Under the HLS scheme we improved access into the scheduled ancient monument (SAM). The project was overseen by English Heritage and their appointed ar...
This project, part of the Higher level Stewardship a Scheme in place at the estate was to replicate the original style of gates which were in situ fro...
We are currently involved in a local project to convert recently felled Larch timber and add value to the product by preparing it for the saw mill. Th...
330 metres of cleft sweet chestnut fencing has been Installed this October for the National Trust at Hanbury Hall to recreate the "semi circle" of the...
Path under construction with the Mansion house and Chapel in background.
Autumn 2015 saw Elc contractors ltd awarded a prestigious contract at Compto...